State Orders Metro to Replace Section of Expo Line Track

Agency told to improve automatic protection system.

By City News Service

State utility and transportation regulators ordered local transportation officials to replace a stretch of faulty track where the Blue Line and recently opened Expo light rail line meet downtown, it was announced Tuesday.

The California Public Utilities Commission also ordered the Los Angeles County Metropolitan Transportation Authority to finish installing an automatic train protection system near the intersection of Flower Street and Washington Boulevard downtown.

Regulators are worried that a southbound Blue Line train might derail as cars make a slow, but sharp 90-degree left turn onto Washington.

Metro staff noticed last fall that wheels on some Blue Line cars were experiencing excessive wear at the junction, commonly referred to as a frog.

Crews added a separate piece of metal to try and fix the problem, but at least two breaks were detected in the new weld, according to Emory J. Hagan, head of the CPUC’s Consumer Protection and Safety Division.

In a letter sent Friday to Metro CEO Art Leahy and Expo Construction Authority CEO Rick Thorpe, Hagan criticized the officials for not immediately notifying regulators of the cracks.

Hagan also said the automatic train protection system, which notifies operators of potential problems, has not been working — in violation of conditions set in March for opening the $930 million Expo Line.

Officials opened a truncated, 7.9-mile stretch of the Expo Line, including the junction, from downtown to near Culver City in April. A second station has since opened in Culver City.

“Our concern is with the safety of your light rail vehicles,” Hagan wrote.

Local transportation officials sought to assure riders that the trains are safe.

“We want to assure the public that Metro and the Expo Construction Authority have been monitoring these issues for some time, and at no time was safety ever compromised,” Leahy and Thorpe said in a joint statement. “Trains have made over 100,000 trips through this junction area traveling less than 10 miles per hour.”

The officials said the section of track in question was fixed on Friday, and they have been complying with orders to do visual and ultrasonic inspections of the track.

“Daily inspections will continue while we resolve this issue with the CPUC,’’ their statement said. “Metro and the Expo Construction Authority will ensure the work is performed to the highest standard and will accept nothing less.”

Print This Post Print This Post

July 19, 2012  Copyright © 2012 Eastern Group Publications, Inc.

Comments

One Response to “State Orders Metro to Replace Section of Expo Line Track”

  1. Interurbans on July 20th, 2012 5:05 pm

    Interesting that in the day of the streetcar 50 plus years ago there were 25 plus junctions some much more complicated in greater Los Angeles and they had no such problems weather it was First and Broadway, Broadway and 11th ,7th and San Pedro 7th and Grand or 6th and Main etc. Many may still be in place under the pavement. In that era they were able to completely change out an interception of track work in 2 evenings and have everything paved the next night. So in our modern era with all kinds of new and improved technology the MTA or their contractors can’t get it right. Also “back then” they seemed to be able to operate the service every 2 to 3 minutes in all directions without the fancy signal safety system. They actually depended on the ability and competence of the train operators. All worked well then, why not today? Bus drivers with a whole lot more to do can manage not to run into each other. Whatever happened to KISS?

Comments are intended to further discussion on the article topic. EGPNews reserves the right to not publish, edit or remove comments that contain vulgarities, foul language, personal attacks, racists, sexist, homophobic or other offensive terminology or that contain solicitations, spam, or that threaten harm of any sort. EGPNews will not approve comments that call for or applaud the death, injury or illness of any person, regardless of their public status. Questions regarding this policy should be e-mailed to service@egpnews.com.